Lakeshore Boulevard Force Main Improvements

Share

Willoughby, Ohio

CT Consultants provided design, construction administration and inspection of approximately 5,300 feet of 16-inch ductile iron force main and appurtenances.  The project included the installation of the pipe along and across a busy state highway adjacent to both residential and commercial property while maintaining access and through traffic during construction. 

The work also included a 292 foot long bore under the Chagrin River to reach the treatment plant headworks as well as the installation of valve chambers and a package pump station to service a marina.  Finally the project included the supply and installation of three new pumps, with 12-inch diameter impellers, in an existing pump station.

Comments are closed.